Work continues on 222nd Street Southwest as contractors are completing curbs and sidewalks on the north side of the street between 39th and 44th Avenues West in Mountlake Terrace.
The $800,000 project is in its final stages after a new water main, valves, connections and hydrants were installed this past fall. There is no formal finish date for the work due to its dependence upon good weather for completion.