Pavement Repair Projects Underway

Pavement repair projects are underway along 212th St SW between the Interurban Trail and 52nd Ave W, 216th St SW between the Interurban Trail and 66th Ave W, and 244th St SW between 56th and Cedar Way. Temporary parking restrictions, single lane closures and minor delays are anticipated with this work.

AA Asphalting Inc. is completing this work in advance of and in conjunction with the 2011 Chip Seal Project that will apply a new wear layer on significant portions of collector streets in the city.

Many portions of these heavily traveled routes are in need of significant repair including restoring the base road material. This contract provides for repair of the base road to enhance the effectiveness of the Chip Seal Project.

The chip seal work consists of applying crushed rock to a liquid asphalt layer that is applied to the existing road surface.

Leave a Reply

Your email address will not be published. Required fields are marked *

Real first and last names — as well as city of residence — are required for all commenters.
This is so we can verify your identity before approving your comment.

By commenting here you agree to abide by our Code of Conduct. Please read our code at the bottom of this page before commenting.